| If you're facing a particularly challenging trench job, give Coble Trench Safety a call to learn how we can help you get it right the first time. |
Atlanta, GA
1.877.312.1776 |
Baltimore, MD
1.866.951.0809 |
Birmingham, AL
1.877.312.1782 |
Charleston, SC
1.866.957.3624 |
Charlotte
1.877.587.3624 |
D.C. / Northern VA
1.866.887.3624 |
Greensboro (Corporate)
1.866.587.3624 |
Greenville, SC
1.877.312.1780 |
Jacksonville, FL
1.877.312.1783 |
Knoxville, TN
1.877.312.1781 |
Myrtle Beach, SC
1.866.586.9404 |
Norfolk, VA
1.866.975.3490 |
Raleigh
1.888.587.3624 |
Richmond, VA
1.866.887.3630 |
| Click links in red above for more detailed information. |
| CTS also offers Competent Person for Trench & Excavation training, as well as Confined Space Entry training. To see available dates and sign-up CLICK HERE |
|
The
Scenario
The power line pole's presence presented a
challenging obstacle that would restrict the
operational performance of the crew to some extent,
as well as the protective system, since there was
unstable dirt on one end of the excavation
surrounding the pole. The project was under a
very tight schedule with a sewer line scheduled for
installation the next day. In addition to
these challenges, the protective system would also
have to fall within the lifting capacity of a rubber
tire backhoe on the jobsite.
The
Solution
Casey Willett met with the contractor to discuss the
unique requirements of the project. Working
back from the necessary dimensions, Casey proposed
protective systems options that would provide the
requisite degree of protection on the project.
After discussions, the contractor elected to use a
combination of a corrugated wall aluminum trench
shield. The corrugated wall aluminum trench
shield would provide the shoring for the 8' long and
10' depth while also working within the lifting
capacity of the rubber tire backhoe. The
aluminum trench shield would be rotated 90 degrees
and installed on its side to provide the protection,
which is permissible with manufacturer's tabulated
data for the product. The open sides of the
shield would be shored with hydraulic vertical
shores with finn form as the sheeting, which could
easily be installed by two workers or light
machinery.
The equipment was delivered promptly and installed
quickly with little difficulty. The system was
tailored to the jobsite of the customer and the
unique set of restrictions affecting the system.
The contractor was very satisfied with the attention
afforded by Casey to the project and ensuring the
equipment was delivered when it was needed.
  |