| If you're facing a particularly challenging trench job, give Coble Trench Safety a call to learn how we can help you get it right the first time. |
Atlanta, GA
1.877.312.1776 |
Baltimore, MD
1.866.951.0809 |
Birmingham, AL
1.877.312.1782 |
Charleston, SC
1.866.957.3624 |
Charlotte
1.877.587.3624 |
D.C. / Northern VA
1.866.887.3624 |
Greensboro (Corporate)
1.866.587.3624 |
Greenville, SC
1.877.312.1780 |
Jacksonville, FL
1.877.312.1783 |
Knoxville, TN
1.877.312.1781 |
Myrtle Beach, SC
1.866.586.9404 |
Norfolk, VA
1.866.975.3490 |
Raleigh
1.888.587.3624 |
Richmond, VA
1.866.887.3630 |
| Click links in red above for more detailed information. |
| CTS also offers Competent Person for Trench & Excavation training, as well as Confined Space Entry training. To see available dates and sign-up CLICK HERE |
|
The
Scenario
The project would have to be dug in one day and a
structure built so that traffic could return to
normal the next day, so that the fire lane remained
fully operational as did deliveries to the hospital.
In addition to the rigid time demands of the
project, the working area would be very tight with
very little working room and even less area for
staging equipment.
The
Solution
The contractor and Jarrette Strickland
discussed the project while it was bidding and began
to explore ways to address the need to shore the
excavation as well as how to best return traffic
flow in one day while leaving the excavation
accessible. After a few conversations, a
solution was finally reached. Steel trench
shields would form the shoring basis for the project
and had to be dug in the during that 1 day window.
The shields would be stacked to provide the
necessary 12 feet of depth and then a traffic deck
would have to be assembled to allow traffic flow to
return to normal.
The design for the traffic deck was to rely upon
steel beam that would stretch the excavation and
extend on each side of the excavation for stability.
Once the beam was set, steel road crossing plate
would then be welded to the beam to provide a sturdy
and secured traffic deck that would allow the
roadway to be functional, while also allowing the
excavation to remain open below the traffic deck.
The excavation would then be accessible from the
ends which were not covered by the traffic deck.
The system was well-designed and helped provide the
appropriate combination of worker safety as well as
the needs of the project's owner. The system
functioned very well and the project was completed
without incident and interruption other than the 1
day installation and 1 day removal for the system.
  |