| If you're facing a particularly challenging trench job, give Coble Trench Safety a call to learn how we can help you get it right the first time. |
Atlanta, GA
1.877.312.1776 |
Baltimore, MD
1.866.951.0809 |
Birmingham, AL
1.877.312.1782 |
Charleston, SC
1.866.957.3624 |
Charlotte
1.877.587.3624 |
D.C. / Northern VA
1.866.887.3624 |
Greensboro (Corporate)
1.866.587.3624 |
Greenville, SC
1.877.312.1780 |
Jacksonville, FL
1.877.312.1783 |
Knoxville, TN
1.877.312.1781 |
Myrtle Beach, SC
1.866.586.9404 |
Norfolk, VA
1.866.975.3490 |
Raleigh
1.888.587.3624 |
Richmond, VA
1.866.887.3630 |
| Click links in red above for more detailed information. |
| CTS also offers Competent Person for Trench & Excavation training, as well as Confined Space Entry training. To see available dates and sign-up CLICK HERE |
|
The
Scenario
The highway that would have to be traversed
presented the major obstacle present on the project;
however, that was known from the onset and had been
remedied by the use of a bore pit. The shoring
system would have to be designed to provide enough
working room for the boring tool to be set and
operate.
The
Solution
Brett Sondergard met with the contractor during the
initial stages of the project and began to construct
initial needs for the shoring system with the help
of the contractor. Brett and the contractor
met several times to discuss the project and refine
the previous assumptions that had been made.
As the project grew closer, the shoring dimensions
had been determined and it was simply a process of
coordinating the delivery of the system to meet the
contractor's project schedule.
The contractor elected to use an 8 feet tall steel
trench shield with a 4 feet tall steel trench shield
stacker to provide the requisite shoring for 12 feet
of depth. The steel trench shields were then
capped with steel plates on both ends to provide
full soil support. After traffic had been
diverted and it was time for the bore, the steel
plate adjacent to the road was removed and the
boring tool began the bore that would allow the new
water line to be connected to the existing line.
The project went very smoothly and produced no
incidents with respect to the shoring system.
The contractor was very satisfied with the knowledge
and attentiveness of the Coble Trench Safety staff,
which allowed for a more thorough focus upon the
project as opposed to worrying with the shoring
system.  |