| If you're facing a particularly challenging trench job, give Coble Trench Safety a call to learn how we can help you get it right the first time. |
Atlanta, GA
1.877.312.1776 |
Baltimore, MD
1.866.951.0809 |
Birmingham, AL
1.877.312.1782 |
Charleston, SC
1.866.957.3624 |
Charlotte
1.877.587.3624 |
D.C. / Northern VA
1.866.887.3624 |
Greensboro (Corporate)
1.866.587.3624 |
Greenville, SC
1.877.312.1780 |
Jacksonville, FL
1.877.312.1783 |
Knoxville, TN
1.877.312.1781 |
Myrtle Beach, SC
1.866.586.9404 |
Norfolk, VA
1.866.975.3490 |
Raleigh
1.888.587.3624 |
Richmond, VA
1.866.887.3630 |
| Click links in red above for more detailed information. |
| CTS also offers Competent Person for Trench & Excavation training, as well as Confined Space Entry training. To see available dates and sign-up CLICK HERE |
|
The
Scenario
Given the inability to tear up the existing road,
the contractor was left with the option of
horizontal boring. The shoring system would
have to allow a suitable working area for the boring
machine to operate within to form the boring pit.
The
Solution
During the meeting with the contractor, John
Knighten helped the contractor determine the
requirements of the boring machine and the project
that would affect the shoring system. The
range of motion for the boring tool was the biggest
issue. The contractor was working within a
tight budget and wanted to use steel trench shields
as the protective system; however, conventional
steel spreader pipes would not provide the vertical
pipe clearance that the boring tool required.
After a brief feasibility analysis, John presented
the option of combining the steel trench shield with
steel arch spreaders to achieve the necessary
vertical clearance. Standard 8 feet tall
trench shields typically have vertical pipe
clearances of approximately 65 inches; however, the
use of a steel arch spreader can increase the
vertical clearance to approximately 8 feet or 96
inches - a substantial difference. The
contractor considered this option along with a few
other options that had been provided; however,
ultimately elected to employ the steel trench shield
and arch spreader system.
The arch spreader provided the necessary vertical
clearance so that the boring tool could function
unimpeded. The system provided a safe working
environment for the workers and protected against a
soil collapse while achieving maximum functionality.
The system worked within the contractor's budget and
allowed the contractor to focus efforts on the
project's completion and not worrying with the
protective system.
  |